Search WWW          Hopkinton.org
 Engineering Department  

These photos show the progress of the Fruit Street Wastewater Treatment Facility (WWTF) and Force Main Projects that began this spring. The Force Main portion of the project included installation of a 6” high-density polyethylene (HDPE) pipe from the WWTF on the Fruit Street Property out to Fruit Street all the way to Saddle Hill Road .

The Force Main Project is close to 80% complete with final testing of the force main and paving on Fruit Street still to be completed. Paving on Fruit Street will be completed next spring which will close out the project. This project will be completed on schedule and all indications are it will come in under budget. J.P. Cardillo is the General Contractor for the force main project.

The WWTF project is also under way with construction started this spring. The majority of the clearing and site work have been completed including pouring of concrete for the wastewater treatment tanks and process building. Construction of the process building is scheduled to begin within a month and the majority of the concrete work for the treatment tanks and process building foundation and walls will be completed shortly.

The WWTF is approximately 15% complete but will ramp up considerably over the upcoming months. It is scheduled to be completed next fall/winter with startup of equipment beginning next spring. Upcoming milestones will be installation of the disposal field, installation of all site piping, construction of the process building, completion of remaining site work, completion of the access road and final startup and testing.

The Department of Public Works and the Facilities Department are monitoring the project and working with the Design Engineer, AECOM, who is also providing onsite resident engineering services for the project. Waterline Industries is the General Contractor for the WWTF project.

Update provided by: David Daltorio, P.E. - Town Engineer/Facilities Coordinator

CLICK ON ANY PHOTO TO
SEE A LARGER IMAGE

Completed Treatment Tanks Concrete Pour and Reinforcing Steel Force Main Trench Preparation of Treatment Tank Foundation Preparing Process Building Floor Slab and Foundation Preparing Process Building Foundation Setup for Force Main Installation Splicing of Force Main

Hopkinton, MA 01748 | Contact Us